Aerial view of a housing development site in WA, showcasing civil infrastructure works with newly paved roads, red earth lots, construction equipment, scattered vehicles, and completed houses beside undeveloped plots.

Explore Our Experience

We are proud to deliver for government, private industry and the resource sector. To learn more about our current and completed projects, contact our team for detailed case studies and project sheets.

Aerial view of a large industrial port with docks, ships, cranes, and warehouses along a winding river, surrounded by expansive flatlands and scattered infrastructure under a clear sky.

Sea Wall Relocation & Dredging

This complex project involved dredging and sea wall relocation in an active port. It required precision, environmental care and a highly coordinated delivery approach from our local team.

The Challenge

The Pilbara Ports Authority sought a contractor capable of relocating a section of sea wall and executing land-based dredging within an active port environment. This required overcoming numerous challenges: sensitive marine conditions, fluctuating tides and regulatory oversight for environmental protection. The project needed to proceed without disrupting daily port operations, requiring precise planning and real-time responsiveness. These technical demands were further compounded by a strict delivery window, making reliability and resource readiness essential to successful execution.

The Solution

Norwest Group mobilised an excavator-mounted dredge head and GPS-enabled earthmoving equipment to undertake the dredging and relocation works. Our internal logistics team supplied all required materials, while our experienced operators managed daily coordination with port authorities to work within the live operational zone. We implemented environmental controls and daily site monitoring to mitigate impact on adjacent marine areas. Drawing on our local knowledge and equipment availability, we staged the works to meet access windows and delivery milestones.

The Result

The sea wall and dredging works were completed within the allocated timeframe and budget. The outcomes included improved port functionality and protection of surrounding infrastructure. More importantly, our performance demonstrated Norwest Group’s capability to deliver complex, coastal interface projects in high-stakes environments. The project strengthened our relationship with the Pilbara Ports Authority and confirmed our credentials as a preferred contractor for marine-adjacent civil works across regional Western Australia.

Sea Wall Relocation & Dredging

Aerial view of a construction site with three yellow excavators and a small compactor working on uneven, rocky terrain surrounded by dirt piles and tracks.

Subdivision Development for Government Land

This project involved delivering subdivision works for residential land release. Norwest Group was engaged for full-scope site preparation, including trenching, road formation and pad construction under tight scheduling constraints.

The Challenge

Development WA required full-scale civil works for a residential land release, including road construction, drainage systems and service corridors. The remote location posed logistical challenges and a strict delivery schedule was enforced due to funding and planning milestones. High standards of compliance and communication were also required, as the works had to align with government protocols, community engagement plans and multi-stakeholder timelines.

The Solution

Norwest Group mobilised its in-house fleet and resources to ensure delivery certainty. GPS-enabled equipment delivered precise trenching and road formation, while our site crew maintained close coordination with planners, surveyors and local government stakeholders. In-house material supply reduced risk and daily reporting kept the project aligned with programme milestones. We integrated site supervision and traffic control to ensure safety and continuity throughout.

The Result

The subdivision works were completed to spec, on time and with full compliance. Civil infrastructure was handed over ready for construction commencement ahead of schedule. This success reinforced Norwest Group’s ability to deliver public infrastructure works within the expectations of government partners. The project also strengthened our standing on the Development WA panel and demonstrated our full-scope capability in land development environments.

Subdivision Development for Government Land

A yellow excavator lifts dirt onto a mound at a construction site, while another heavy machine moves nearby, both surrounded by dust and trees in the background.

Evaporation Pond & Dredging Support

This project included excavation of evaporation ponds and supporting the relocation of a sea wall through land-based dredging. Norwest was selected for our equipment, capacity and regional delivery record.

The Challenge

The project involved the excavation of large-scale evaporation ponds and supporting marine works in an area with high-moisture soils and access constraints. The biggest challenge was maintaining productivity while sequencing works around other contractors on site. Additionally, the ground profile required careful shaping to ensure adequate water retention and environmental regulations governed material movement and disposal. The team needed to balance accuracy, volume and environmental compliance while keeping the works within the port’s larger project programme.

The Solution

Norwest Group mobilised GPS-enabled earthmoving equipment and experienced operators to deliver shaping and excavation works to specification. We implemented a staged delivery plan that aligned with the marine contractor’s schedule, avoiding delays to interconnected activities. Water management controls were introduced to stabilise the site during excavation. Our crushing and screening equipment processed materials for reuse, while internal logistics supported efficient haulage and on-site distribution. The team also provided regular updates to ensure transparent progress reporting.

The Result

The evaporation ponds were completed on time and in accordance with project specifications, providing long-term environmental functionality for the port site. Our work contributed to broader marine and land interface improvements under the client’s infrastructure upgrade strategy. The successful integration of earthworks, sequencing and stakeholder coordination reinforced Norwest’s role as a preferred contractor for high-risk, high-value civil packages. The project highlighted our ability to manage complex works with self-performed capability and collaborative execution.

Evaporation Pond & Dredging Support